Construction Updates
The façade of the John G. Rangos Sr. Research Building is nearly complete.
Summer 2008
Main Hospital Building
- Sidewalks around the campus are 60 percent complete. Work continues along Garwood Way.
- Work on the elevators is nearing completion. Testing began in June.
- Drywall installation is substantially complete.
- Ceiling framing and ceiling tile installation continue throughout the building.
- Ceramic tile in the restrooms is 90 percent complete. Tiling the kitchen floor has started and will be complete by July 2008.
- Carpet and sheet flooring installation continue. Carpet is installed in areas on levels 5 through 9.
- Casework installation continues on levels 1 thru 3.
- Wall rail installation is progressing on levels 8 and 9 and in the basement.
- Ceiling work in the sixth floor atrium is substantially complete. Work has begun on the Howard Hanna Healing Garden.
- Johnson Controls is installing nurse call, security, fire alarm and phone systems/devices throughout the building.
- Trees have been delivered to the site to begin street-level landscaping.
Central Plant
- Construction is substantially complete. Minor work and testing will continue throughout the summer and early fall.
John G. Rangos Sr. Research Center and North Garage
- Site grading and site concrete installation have started around the North Garage.
- The loading dock area has been completed and is being used for campus deliveries.
- Brick veneer work is continuing on the west elevation.
- Exterior building cladding work is substantially complete.
- Interior work is nearing completion. Flooring and casework are almost complete on the lab floors. Interior work continues on levels 1 to 4. All work is scheduled to be substantially complete by July 7, 2008. Punch list work and commissioning work will continue into late August.
Faculty Pavilion
|
| Exterior cladding work is complete on this pedestrian bridge linking offices in the Faculty Pavilion to the main hospital building. |
- All exterior cladding work is complete, including the cladding of the bridge connecting the Pavilion to the Main Hospital.
- All interior work is substantially complete. This includes all of the furniture systems.
- Life safety and elevator testing are ongoing.
Administrative Office Building
- Painting, flooring and ceilings are proceeding on levels 6 thru 4. Casework installation has started on these upper floors.
- Prime and first coat of paint proceeding on levels 3 and 2.
- Drywall installation continues on level 1.
- This building is progressing to be substantially complete by July 30, 2008.